Mariposa Avenue Safe Routes to School - Phase 3

45445906-construction-cone-character-with-loudspeaker

Mariposa Avenue Safe Routes to School - Phase 3 (Mariposa SR2S PH3) construction began May 1, 2019 along the east side of Mariposa Ave. from Northridge Dr. to Eastgate Circle. The project will continue the installation of curb, gutter, sidewalk and street lighting for the Safe Routes to School.  Construction is expected to last about six months, ending in October. Please be cautious in construction zones - Speed Limit 25 miles per hour.  

Mariposa Avenue SR2S Phase 1 was completed in 2007.

Mariposa Avenue SR2S Phase 2 was completed in 2013. 

Mariposa Avenue SR2S Phase 4 is in preliminary design and right of way acquisition.